By David Gold

FIFA inspect_Maracan__Sept_8September 8 - A delegation from FIFA and Brazil 2014 have visited the renovation works on the iconic Maracanã Stadium in Rio de Janeiro.


It will host the final of the World Cup in 2014, as well as the Opening and Closing Ceremonies of the Rio 2016 Olympic and Paralympic Games.

The Maracanã is one of the six stadiums set to host matches at next summer's Confederations Cup, including the final – the traditional practice run for the World Cup.

Undergoing a $643 million (£400 million/€454 million) renovation, the stadium will host three games at the Confederations Cup and a further seven at the World Cup.

The vice-governor of Rio de Janeiro, Luiz Fernando Pezão, met with the delegation and informed them that nearly two thirds of the works on the stadium had been completed.

Pezão said that work on the stadium should be complete by February 2013, although it was originally scheduled for completion by the end of this year.

Maracan renovations_seen_by_FIFA_Sept_8Renovation work at the Maracanã as seen by the FIFA and Brazil 2014 delegates 

Last year the stadium's roof had to be removed because of faults, but now that has been resolved progress appears to be moving according to plan.

"The aim is to be able to receive the press, the athletes, the referees, the fans in the best possible conditions," the World Cup organising committee executive director of operations Ricardo Trade said.

"There's nine months to go to the Confederations Cup and we're already beginning to feel the adrenaline rush."

The visit to the Maracanã is the first part of the delegation's visit to a number of World Cup host cities, which will take in Belo Horizonte, Recife, Salvador, Fortaleza, Brasilia and São Paulo.

The slow pace of construction of the stadiums for the World Cup has been a concern but appears to have picked up in recent months.

Recife stadium_construction_workThe slow pace of construction work at Recife continues to be a worry

São Paulo will stage the opening game of the World Cup at its newly constructed stadium, 48 per cent of which is complete despite work only beginning last year.

At the close of August, only stadiums in Cuiabá, Curitiba, Manaus and Natal were less than 50 per cent complete.

Only 51 per cent completed, Recife is the biggest concern for FIFA.

It could yet lose the right to host games during next year's Confederations Cup.

Contact the writer of this story at [email protected]


Related stories
August 2012: Brazil will meet expectations for Olympics and World Cup, insists Sports Minister
May 2012: Brazil plans "green" World Cup as Maracanã Stadium embraces solar power
April 2012: Part-rebuilt Maracanã Stadium opens to the public
November 2011: Police force stationed in favela close to Maracanã
October 2011: Maracanã roof removed as $643 million modernisation continues